The culvert is moving along as another forty feet of culvert has been installed and back-filled with sand leaving 90 feet remaining! As you can see in the photo below, the culvert sections are staged and ready to go for the next 30 foot section. The crew estimates that they will have the project completed by December 31 if weather permits. Dredging of the remaining approximately 18,000 cubic yards of sand in Wreck Pond began again and will continue through December 31. The Wreck Pond Citizen Science Monitoring Program was kicked off this past weekend as well. See below for a copy of the handbook and to learn more about the program. If you are interested in getting involved, email Julie at julie@littoralsociety.org for more information. ![]()